Post by AirTravel on Oct 22, 2014 22:05:01 GMT 7
Defence projects at key traffic points in the city center of Hue city and people used to call this the prime location is an area of red soil "diamond", "land of gold".
Knowing how the province's Council meeting, then the meeting Hue City People's Council delegates have spoken many times to ask questions about this project.
But things just stop at the level of "know, so hard to say forever". Even now these projects are located "real war plan." While the recovery is very difficult.
Soft yellow soil which
First, since the project supermarkets, office buildings Viwaseen located in the center of Hue city, the intersection point between Ly Thuong Kiet Street - Hanoi - Nguyen Tri Phuong Ngo Quyen, with an area of 2,577 m2, high 15 floor.
New construction projects and lying partly between rain and sun exposure of the central years. Access, the project to build a hotel UHotel Hue, area 7,000 m2 located in a beautiful location with two road frontage on Ly Thuong Kiet Street - Hanoi.
When the winning auction Lot, investors to pressure from 8/2011 126 bored piles. Due to difficulties in access to finance, construction project was stopped in late 2011.
Then in 2009, PPC procedures for Investment JSC Petrolimex Hue Tourism leased 4,575 m2 in area No. 50A Hung Vuong, in 50 years time to build Petrolimex hotel zone.
After being granted an investment certificate, the investor only 501 piles pressure and some other small items. Construction work has stopped, slow progress for 2 years.
Project tourism service center is located at the foot HuePlaza Phuxuan in dynamic regional center south of the city by Hue Tourism Corporation as an investor.
Licensed investment in January 4/2008. The company is committed to complete in the fourth quarter / 2012. The project was done partly with 5 floors, 1 basement floor area 5.728m2 third quarter / 2011 and construction was halted so far.
In particular, in the project land line number 4 Group Hanoi Vietnam Posts and Telecommunications (VNPT) purchased through auction winners transfer of land use rights for a total value of 130.7 billion in March / in 2012.
Since winning the auction date so far, investors have not been implemented in the construction field. Cause, due to the capital to participate in the auction lot may include Investment Company Urban Infrastructure Development and UCID - units into partnership with VNPT.
As a result, the Company adjusted the proposal PPC decided to supplement the partnership units to win the auction results plot. However, this problem can not be solved by the problems of law provisions.
Revoked if the project continues to progress slowly
As reported by the Department of Planning and Investment (MPI) Hue sent to the press agency, in recent years the province has conducted 20 recovery projects (of Chan my- Lang 6 industrial zone 4; outside industrial parks, economic zones 2).
As for the hotel project Song Da - Thang Long Uhotel at Ly Thuong Kiet Street; commercial office buildings, hotels and luxury apartments in Hanoi street - Ly Thuong Kiet investment volume of 80% of total investment; Supermarket projects and building rental Viwaseen Corporation at No. 2 Nguyen Tri Phuong slow deployment of temperance.
Under the provisions of the Land Law if recovery projects, land acquisition, Thua Thien Hue province does not have the budget to compensate investors or compensation but no demand for investment assets, will generate the other waste.
About the buildings in the Gold Lot at Hue City under construction limping, Le Dinh Khanh - Deputy Director of the Department of Planning and Investment said last time PPC allows investors looking for partners capacity for investment cooperation or transfer projects, besides PPC has introduced a number of qualified partners for co-investment or project assignment.
To date hotel projects - Song Da Thang Long JSC Uhotel by Song Da Thang Long investors have turned to private enterprise Ngoc Thien Thanh list which has the financial capacity to continue.
In addition, the province has issued decision 1629 / QD-PPC dated 08/07/2014 on the establishment of working group examine the progress made and propose ways to handle a number of projects in the province delayed level, including projects in Ly Thuong Kiet and Nguyen Tri Phuong includes: hotels project Song Da - Thang Long Uhotel, office buildings, commercial, hotels and luxury apartments in Hanoi 4 Viwaseen or supermarket projects and buildings leased by the Company of shares and Viwaseen building at No. 2 Nguyen Tri Phuong Street in the direction of allowing extended under the provisions of the Land Act 2013 if the project continued slow progress the project and not recovered compensation for land and assets attached to land.
Knowing how the province's Council meeting, then the meeting Hue City People's Council delegates have spoken many times to ask questions about this project.
But things just stop at the level of "know, so hard to say forever". Even now these projects are located "real war plan." While the recovery is very difficult.
Soft yellow soil which
First, since the project supermarkets, office buildings Viwaseen located in the center of Hue city, the intersection point between Ly Thuong Kiet Street - Hanoi - Nguyen Tri Phuong Ngo Quyen, with an area of 2,577 m2, high 15 floor.
New construction projects and lying partly between rain and sun exposure of the central years. Access, the project to build a hotel UHotel Hue, area 7,000 m2 located in a beautiful location with two road frontage on Ly Thuong Kiet Street - Hanoi.
When the winning auction Lot, investors to pressure from 8/2011 126 bored piles. Due to difficulties in access to finance, construction project was stopped in late 2011.
Then in 2009, PPC procedures for Investment JSC Petrolimex Hue Tourism leased 4,575 m2 in area No. 50A Hung Vuong, in 50 years time to build Petrolimex hotel zone.
After being granted an investment certificate, the investor only 501 piles pressure and some other small items. Construction work has stopped, slow progress for 2 years.
Project tourism service center is located at the foot HuePlaza Phuxuan in dynamic regional center south of the city by Hue Tourism Corporation as an investor.
Licensed investment in January 4/2008. The company is committed to complete in the fourth quarter / 2012. The project was done partly with 5 floors, 1 basement floor area 5.728m2 third quarter / 2011 and construction was halted so far.
In particular, in the project land line number 4 Group Hanoi Vietnam Posts and Telecommunications (VNPT) purchased through auction winners transfer of land use rights for a total value of 130.7 billion in March / in 2012.
Since winning the auction date so far, investors have not been implemented in the construction field. Cause, due to the capital to participate in the auction lot may include Investment Company Urban Infrastructure Development and UCID - units into partnership with VNPT.
As a result, the Company adjusted the proposal PPC decided to supplement the partnership units to win the auction results plot. However, this problem can not be solved by the problems of law provisions.
Revoked if the project continues to progress slowly
As reported by the Department of Planning and Investment (MPI) Hue sent to the press agency, in recent years the province has conducted 20 recovery projects (of Chan my- Lang 6 industrial zone 4; outside industrial parks, economic zones 2).
As for the hotel project Song Da - Thang Long Uhotel at Ly Thuong Kiet Street; commercial office buildings, hotels and luxury apartments in Hanoi street - Ly Thuong Kiet investment volume of 80% of total investment; Supermarket projects and building rental Viwaseen Corporation at No. 2 Nguyen Tri Phuong slow deployment of temperance.
Under the provisions of the Land Law if recovery projects, land acquisition, Thua Thien Hue province does not have the budget to compensate investors or compensation but no demand for investment assets, will generate the other waste.
About the buildings in the Gold Lot at Hue City under construction limping, Le Dinh Khanh - Deputy Director of the Department of Planning and Investment said last time PPC allows investors looking for partners capacity for investment cooperation or transfer projects, besides PPC has introduced a number of qualified partners for co-investment or project assignment.
To date hotel projects - Song Da Thang Long JSC Uhotel by Song Da Thang Long investors have turned to private enterprise Ngoc Thien Thanh list which has the financial capacity to continue.
In addition, the province has issued decision 1629 / QD-PPC dated 08/07/2014 on the establishment of working group examine the progress made and propose ways to handle a number of projects in the province delayed level, including projects in Ly Thuong Kiet and Nguyen Tri Phuong includes: hotels project Song Da - Thang Long Uhotel, office buildings, commercial, hotels and luxury apartments in Hanoi 4 Viwaseen or supermarket projects and buildings leased by the Company of shares and Viwaseen building at No. 2 Nguyen Tri Phuong Street in the direction of allowing extended under the provisions of the Land Act 2013 if the project continued slow progress the project and not recovered compensation for land and assets attached to land.